1 / 24

A project manager is leading a predictive project within a functional organization. During execution, an unforeseen issue requires additional work, increasing project costs. Who should the project manager MOST LIKELY escalate this need for additional funding to?

2 / 24

One month after starting a new job, a project manager is given a new project to lead. They're a little anxious because it's their first time managing a hybrid project. The project manager was told that an external auditor will check the project's quality next week. What should the project manager expect from this audit?

3 / 24

A project manager works for an NGO, leading a campaign to educate women leaving below poverty line While contacting edutech companies to convince them to take part in this campaign, they enumerate the many benefits this partnership can bring them. Which of the following are considered tangible benefits of participating in this campaign? (Select two)
1. Increased revenue
2. Stronger brand awareness
3. Improved reputation
4. Tax benefits for sponsoring an NGO

4 / 24

Maslow’s hierarchy of needs breaks down human needs dictating their behavioral motivation. At the bottom, it identifies physiological needs such as food, water, warmth, and rest. Place the rest of the other needs in ascending order in their right position:
1.Physiological Needs,
2.Safety and Security Needs
3.Love and Belonging Needs
4.Esteem Needs
5.Self-Actualization Needs

5 / 24

A project manager is leading a software development project using a hybrid approach. During project execution, the new key stakeholder was onboarded the team. When the project manager informed the new key stakeholder that the deliverables were produced using a hybrid project management approach, she asked for proof. How should the project manager address the new key stakeholder’s request?

6 / 24

A project is in its execution phase, with a planned duration of twelve months. After five months, only 40% of the project is completed. The project's SPI is also calculated to be 0.78. Based on this information, how would you describe the project's progress?

7 / 24

After your latest weekly project meeting, the sponsor wanted to know how the project was going. Which of the following technique is used to check the progress of the project?

8 / 24

In the weekly project status meeting, the team provided with information that one of project most important stakeholders has called for the project termination and has stopped supporting it. You being the project manager of this project, what should be the best thing to do next?

9 / 24

What becomes more critical when collaborating with virtual teams?v

10 / 24

Risk planning is an important activity in project management. During one of these meetings, the team allocates $3000 as a contingency fund for a specific, critical risk. The team is working on which risk response strategy?

11 / 24

The team is developing a new resource management system for a client for the features aligned with the business value. Even though the specific functionalities aren't fully defined, the team has created a high-level plan outlining features and their estimated delivery timeframe. The team is working on

12 / 24

As the team facilitator in a Daily Scrum meeting, you hear the team discuss technical roadblocks and an unresponsive stakeholder hindering their progress. These challenges jeopardize achieving the sprint goal. What's the MOST appropriate course of action?

13 / 24

You're new to Agile and find the Kanban board confusing. It displays all the tasks committed to for the current iteration and their current status. You ask your team for clarification, and they explain its uses. Which of the following is LEAST LIKELY to make use of the Kanban Board?

14 / 24

After successfully completing a few sprints, several team members brought up an issue at the most recent daily stand-up meeting: stakeholders were disrupting their work with requests for status updates, including queries about their current tasks and the sprint's progress. What could have prevented this issue?

15 / 24

The project sponsor is looking for a graphical tool that can help understand the progress of each iteration and whether or not it is as per the release plan. The next release is very crucial to the company. Which Agile tool would you recommend the sponsor refer to?

16 / 24

You are new to agile projects and are looking for an agile project leadership approach. As per your findings, agile project manager supports and guides the team to be self-managing. This leadership style involves eliminating impediments, fostering collaboration, and promoting a self-organized team. What is this leadership style known as?

17 / 24

You are overseeing a utility project, which involves both installing data servers and creating new software to record usage. The server installation must follow a strict process, while the software's features might change as development progresses. Given this situation, which project approach would be most appropriate?

18 / 24

You are attending a software development meeting where the team is actively asking questions about features, ensuring alignment on the Definition of Done, and planning how much they can accomplish in the upcoming iteration.

19 / 24

During the implementation of the requirement, the project manager encountered an issue with one of the stakeholders. The stakeholder insisted on modifying features in the current iteration.
Which of the following individuals might the project manager engage to assist in managing difficult stakeholders as needed?

20 / 24

The project manager wants all potential vendors to be fully aware of the procurement requirements before they submit proposals for a new project. The manager calls for a meeting to discuss the scope. Which of the following contract types puts the seller at the highest risk?

21 / 24

A very important client has requested a change that is critical to project success, and the client insists that it be implemented immediately. Following a series of questions with the client, the project sponsor instructs you to proceed with the change. What is your next plan of action?

22 / 24

Prior to scheduling a meeting with the customer, your project team is working towards completing the verified deliverables task to :

23 / 24

As the project manager, you're handling various aspects of the project's cost, to be included in the project management plan. What's included in the project budget but not in the cost baseline?

24 / 24

As the project manager overseeing a project with 100 stakeholders, the team has recognized 15 individuals as key stakeholders. Presently, you're in the process of crafting the stakeholder engagement plan, which acts as a practical roadmap for interacting with stakeholders to enhance project value. Assessing the needs, levels of interest, and potential impact on project success of these key stakeholders will guide the development of action plans. Where can the team locate this information for analysis?